E Squared Marine

E Squared Marine| 8,000 SF PEMB | Friendswood, TX

6.30.20 - This project is complete,

3.30.20 - Crews are wrapping up their work sheeting the building,

3.10.20 - Roof sheeting and siding installation are underway,

3.02.20 - Crews have finished sheeting the east wall and continue to install purlins,

2.27.20 - Crews continue to hang steel and began sheeting the east wall,

2.20.20 - Crewmen began to shake out and assemble the steel,