Word of God Christian Fellowship Church | 12,000 SF FACILITY

8.13.18 - The walls and roof are sheeted. Crewmen are finishing the soffit and installing the trim,

IMG 1949

IMG 1951

IMG 1957

IMG 1958

IMG 1959

 

7.20.18 - Roof sheeting is underway,

IMG 1925

IMG 1928

IMG 1937

7.03.18 - Installing additional purlins. Sheeting continues,

IMG 1730

IMG 1731

6.25.18 - Crewmen have hung all steel and began sheeting the exterior,

IMG 1625

IMG 1626

IMG 1628

IMG 1630

IMG 1631

IMG 1635

IMG 2186

 

6.18.18 - Crewmen have assembled the roof sections and will begin installing once site dries,

WordofGod6.18.18