twitter facebook linkedin

Over 200 years
of combined experience

previous arrow
next arrow
Slider

M&M Erectors

View important updates by M&M Erectors

Inglesia Pentecostal

Inglesia Pentecostal | New 31,116 SF Church Facility 

9.15.21 - Erectors continue to hang steel,

 

8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.

Continue reading

Independence Business Park

Independence Business Park | New 43,000 SF PEMBs | Houston, TX

9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,

 

8.24.21 - Erectors are lifting section of roof for Bldg #4,

Continue reading

Wilson Air Repairs

Wilson Air | Repairs | Houston, TX

6.04.21 - Crewmen are relsealing all roof curbs on Hangars 9 & 10

6.03.21 - Crews are resealing roof curbs on Hangar 10

6.02.21 - Crews are reworking the roof curbs on Hangar and repairing leaks on Hangar 8,

Continue reading

Wilson Air

Wilson Air | Repairs | Houston, TX

11.05.20 - Crewmen are replacing all of the structural bolts and making welding repairs to deteriorated steel rafters,

Continue reading

Ameritex

Ameritex | 30,000 SF PEMB | Conroe, TX

11.02.20 - Crewmen continue to sheet the roof and install medal siding,

9.18.20 - Crewmen continue to sheet the facility,

9.08.20 - Crewmen have progressed to sheeting the roof,

Continue reading

Dianal America

Dianal America | Resheet | Pasadena, TX

10.07.20 - Crewmen are resheeting the walls of the tower,

Continue reading

St. Mary Catholic Church

St. Mary Catholic Church | 15,000 SF Fellowship Hall and 9,000 SF Mezzanine | League City, TX

9.18.20 - Crewmen finished sheeting the mezzanine,

 

9.08.20 - Progress has been made sheeting the mezzanine. Crewmen are welding the perimeter angle and column washers,

Continue reading

St. Patrick's Church

St. Patrick's Church | 5,600 SF | Houston, TX

9.18.20 - Crewmen have progressed to installing purlin straps. Sheeting will soon follow,

9.08.20 - Main frame columns are up. Crewmen have progressed to hanging sections of the roof,

Continue reading

Magellan Midstream Partners

Magellan Midstream Partners | 9,500 SF PEMB | Houston, TX

7.07.20 - Crews continue to hang steel and have made progress with the metal siding installation,

6.19.20 - The building was delivered.

 

Continue reading

E Squared Marine

E Squared Marine| 8,000 SF PEMB | Friendswood, TX

6.30.20 - This project is complete,

3.30.20 - Crews are wrapping up their work sheeting the building,

 

Continue reading

Grizzly

Grizzly | 35,000 SF PEMB | Waller, TX

5.28.20 - Crewmen have completed the office siding, installation, and trim,

4.21.20 - The walls and roof are completely sheeted,

 

Continue reading

Grand Pkwy Professional Buildings

Grand Pkwy Professional Buildings | 3 PEMBs | Richmond, TX

3.13.20 - Crewmen are to erect (1) 49'x89' building, (1) 50'x119' building, and (1) 49'x119' building. They will later return to trim the buildings and install the downspouts. Crews are currently erecting the steel,

 

Continue reading

Hoelscher Doors and Weatherstrip

Hoelscher Doors and Weatherstrip | 192,000 SF | Tomball, TX

3.09.20 - M&M's work on this project is complete,

 

12.30.19 - Macario and his crew are installing trim on the warehouse and finishing the canopies,

Continue reading

Dollar General

Dollar General | 9,100 SF PEMB | Houston, TX

3.02.20 - Crews have hung all steel and have sheeted the exterior,

2.12.20 - Crews will began hanging steel for a new Dollar General on 2.17 for Wright Construction.

 

Continue reading

4121 Clay Road

4121 Clay Road | 9,300 SF PEMB | Katy, TX

12.03.19 - Crewmen continue to trim the office,

10.05.19 - Crews are sheeting the office and warehouse,

9.24.19 - Crews erected all main frame columns and are hanging the purlins,

Continue reading

Traders Village - Joe's Burgers

Traders Village | 4,000 SF Freestanding Joe's Burgers Restaurant | Houston, TX

10.10.19 - Final photos of this project,

9.24.19 - Our work on this project is complete,

 

Continue reading

Traders Village - Subway

Traders Village | 4,000 SF Freestanding Subway Restaurant | Houston, TX

10.10.19 - This project is complete,

9.24.19 - This project is very near completion,

 

Continue reading

26106 Clay Road

26106 Clay Road | 12,000 SF PEMB | Katy, TX

9.13.19 - Our work on this project is complete,

 

8.09.19 - Crewmen are finishing the timwork on the building,

Continue reading

Wilson Air

Wilson Air | 28,000 SF Airplane Hangar and Office Addition | Houston, TX

9.05.19 - Crews completed their work on the hangar doors and have finished the trim. Their work on this project is complete,

 

9.03.19 - Crewmen worked on the rolling hangar doors so group 3 could open and close independently of group 6. Crewmen repaired the weatherstrip after separating the sections of rolling door. Crewmen also installed trim between the existing building and the purlins,

Continue reading

Texcel

Texcel | 42,000 SF Warehouse Expansion | Houston, TX

3.11.19 - This project is nearing completion,

2.20.19 - Installing gutters and downspouts,

2.05.19 - Sheeting continues,

Continue reading

Contact Us

Please let us know your name.
Invalid Input
Invalid Input
Please let us know your email address.
Please let us know your message.
Invalid Input