20213 Binford Rd | New 20,000 SF Trade School | Waller, TX
5.11.22 - Interior buildout continues, but M&M's work on this project is complete.



3.18.22 - The sheeting is complete. Masonry is underway and crewmen will return to trim the building,

2.15.22 - The building exterior is sheeted and trimmed,

1.19.22 - Crews continue to sheet the roof,


1.04.22 - Crewmen continue to hang steel,