Commons at Timber Creek

Commons at Timber Creek | Two 13,020 SF PEMBs | Friendswood, TX

These Industrial Suites are complete,

 

7.17.23 - We will return to trim the building,

Continue reading
  1569 Hits
1569 Hits

Big City Manufacturing

Big City Manufacturing | 23,000 SF | Friendswood, TX

1.23.24 - Final photos,

 

10.25.23 - The building is completely sheeted and gutters are installed,

Continue reading
  504 Hits
504 Hits

SiteOne Landscape Supply Expansion

SiteOne Landscape Supply | 12,000 SF Expansion | Friendswood, TX

1.23.24 - This project is complete,

 

12.14.23 - Crews continue to sheet the building,

Continue reading
  501 Hits
501 Hits

Katy Industrial Suites

Katy Industrial Suites | 26,660 SF Custom Office Condos | Katy, TX

12.14.23 - Final photos,

10.04.23 - Our work is complete on these business suites, 

 

Continue reading
  1199 Hits
1199 Hits

Big Industry Boat and RV Storage

Big Industry Boat and RV Storage | 100,000 SF | Friendswood, TX

These storage units are complete,

 

3.01.23 - The first two buildings are fully sheeted and trimmed. Sheeting continues for the third unit. There will be 13 buildings total.

Continue reading
  860 Hits
860 Hits

Humble Sign Co.

Humble Sign Co. | 35,722 SF | Humble, TX

3.08.23 - Crewmen completed their work hanging steel for this project,

 

2.08.23 - Erectors are hanging steel for the new facility,

Continue reading
  868 Hits
868 Hits

Premier Cryogenics

Premier Cryogenics | 26,000 SF 20-ton Crane-served Manufacturing Facility | LaPorte, TX

10.13.22 - Crewmen are nearing completion installing the metal siding,

 

 

Continue reading
  1270 Hits
1270 Hits

Elite RV

Elite RV | 70,000 SF Concierge Service Storage Center | Waller, TX

7.06.22 - This project is complete,

5.11.22 - Crews are trimming out the wash bay,

 

Continue reading
  1703 Hits
1703 Hits

20213 Binford Rd

20213 Binford Rd | New 20,000 SF Trade School | Waller, TX

 

5.11.22 - Interior buildout continues, but M&M's work on this project is complete.

 

Continue reading
  1814 Hits
1814 Hits

Connect Church

Connect Church | New 12,000 SF PEMB | Montgomery, TX

1.26.22 - The church facility is complete,

11.10.21 - Crewmen have returned to this project to install the final trim,

 

Continue reading
  2077 Hits
2077 Hits

Inglesia Pentecostal

Inglesia Pentecostal | New 31,116 SF Church Facility 

9.15.21 - Erectors continue to hang steel,

 

8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.

Continue reading
  1834 Hits
1834 Hits

Independence Business Park

Independence Business Park | New 43,000 SF PEMBs | Houston, TX

9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,

 

8.24.21 - Erectors are lifting section of roof for Bldg #4,

Continue reading
  1767 Hits
1767 Hits

Wilson Air Repairs

Wilson Air | Repairs | Houston, TX

6.04.21 - Crewmen are relsealing all roof curbs on Hangars 9 & 10

6.03.21 - Crews are resealing roof curbs on Hangar 10

6.02.21 - Crews are reworking the roof curbs on Hangar and repairing leaks on Hangar 8,

Continue reading
  2195 Hits
2195 Hits

Wilson Air

Wilson Air | Repairs | Houston, TX

11.05.20 - Crewmen are replacing all of the structural bolts and making welding repairs to deteriorated steel rafters,

Continue reading
  3222 Hits
3222 Hits

Ameritex

Ameritex | 30,000 SF PEMB | Conroe, TX

11.02.20 - Crewmen continue to sheet the roof and install medal siding,

9.18.20 - Crewmen continue to sheet the facility,

9.08.20 - Crewmen have progressed to sheeting the roof,

Continue reading
  2944 Hits
2944 Hits

Dianal America

Dianal America | Resheet | Pasadena, TX

10.07.20 - Crewmen are resheeting the walls of the tower,

Continue reading
  2500 Hits
2500 Hits

St. Mary Catholic Church

St. Mary Catholic Church | 15,000 SF Fellowship Hall and 9,000 SF Mezzanine | League City, TX

9.18.20 - Crewmen finished sheeting the mezzanine,

 

9.08.20 - Progress has been made sheeting the mezzanine. Crewmen are welding the perimeter angle and column washers,

Continue reading
  2681 Hits
2681 Hits

St. Patrick's Church

St. Patrick's Church | 5,600 SF | Houston, TX

9.18.20 - Crewmen have progressed to installing purlin straps. Sheeting will soon follow,

9.08.20 - Main frame columns are up. Crewmen have progressed to hanging sections of the roof,

Continue reading
  2386 Hits
2386 Hits

Magellan Midstream Partners

Magellan Midstream Partners | 9,500 SF PEMB | Houston, TX

7.07.20 - Crews continue to hang steel and have made progress with the metal siding installation,

6.19.20 - The building was delivered.

 

Continue reading
  2708 Hits
2708 Hits

E Squared Marine

E Squared Marine| 8,000 SF PEMB | Friendswood, TX

6.30.20 - This project is complete,

3.30.20 - Crews are wrapping up their work sheeting the building,

 

Continue reading
  3357 Hits
3357 Hits